Awards
Honorable Mention, BCxA Building Award Excellence, New construction Cx Category, Building Commissioning Association, 2019
Honor Award, American Council of Engineering Companies of Florida, 2018
Hanson helped the Greater Orlando Aviation Authority (GOAA) lift a major project off the ground at Orlando International Airport in Orlando, Florida, with commissioning services for the facility’s South Airport Automated People Mover (APM) Complex and Intermodal Terminal Facility (ITF) expansion. The commissioning of the new APM complex and ITF established the infrastructure for the airport’s South Terminal C, which opened to travelers in September 2022.
Hanson’s team commissioned systems including the major building envelope, mechanical (heating, ventilating and air conditioning [HVAC]) and building automation, plumbing, electrical and life safety for the complex. The project encompassed the design and construction of several facilities with a total conditioned area of approximately 335,000 square feet (greater than five football fields), including the four-story APM and ITF; the intercity Brightline rail; and ground transportation comprising public busing, shuttle buses, taxis and limousines. The facility includes a passenger drop-off lobby; central energy plant (CEP); and six-level, approximately 2,400-space parking garage, which will be expanded to accommodate 5,000 parking spaces. The CEP was also sized to support future expansion, and the project came online during the winter, when the cooling load was low. This, combined with the engineered spare capacity, required adjustments in the CEP sequence of operation. Hanson worked with the contractors to find solutions to operate the cooling equipment safely while maintaining the desired indoor space conditions.
Challenges and lessons
GOAA needed to consider planning for functional performance testing and “tuning” systems within a partially open complex that serves the public, submitting the project for LEED® v4 certification and interfacing the commissioning team’s cloud-based web application with the process and owner’s construction management programs. The building commissioning team helped GOAA meet its sustainability and energy-efficiency goals for the project, including a LEED v4 BD+C (new construction) campus certification, which helps the airport avoid wasted energy and unnecessary depletion of natural resources. The APM and ITF commissioning was an economical and cost-effective solution for GOAA.