Project Summary

Hanson provided pre-construction environmental permitting, construction observation and quality assurance reporting services for the foundations of 55 Vestas 1.8-megawatt wind turbines at the Anacacho Wind Farm in Kinney County, Texas, generating 100 megawatts of power.

Hanson also provided quality assurance construction observations for the duration of the project; reviewed design plans for wind turbine foundations, an electrical substation and electrical transmission lines; and assisted with air-quality permits for the on-site concrete batch plant.